EV charger installation in Westminster, CO

Westminster has its own EV charger permit with specific submittal requirements, and Xcel Energy customers may qualify for a wiring rebate. Here is how the two fit together.

Updated November 18, 2026 · Researched from City of Westminster, Colorado DORA and utility sources

On this page
  1. What the City asks for
  2. Xcel Energy's Charger and Wiring Rebate
  3. Published cost ranges (national)
  4. Westminster permit fee for a charger circuit
  5. Questions to ask before you buy a charger
  6. Frequently asked questions

What the City asks for

Westminster's EV charger permit is applied for in eTRAKiT under Residential Counter, EV Charger, and the City asks applicants to include the manufacturer's installation instructions. (City Resources) Its submittal requirements differ by charger level (City EV charger requirements):

  • Level 1: a site plan or floor plan showing the location of the new receptacle outlet.
  • Level 2 (residential): a site or floor plan showing the charging equipment, plus load calculations for the entire residence and a one-line diagram.

That load calculation is the step that tells you whether your panel can take the charger or needs an upgrade. If a charger is part of a solar project, the City requires a separate permit for the charger. (City Resources)

Xcel Energy's Charger and Wiring Rebate

Xcel Energy Colorado offers a Charger and Wiring Rebate for residential customers. Its page says the rebate requires enrollment in a qualifying Xcel program, that a Level 2 charger needs a dedicated 240-volt circuit, and that applications are submitted through My Account. It also says the EV Accelerate At Home program closed to new Colorado enrollments on July 14, 2026. (Xcel Energy, Charger and Wiring Rebate)

Rebate amounts, eligible chargers and terms change, so check Xcel's current Charger and Wiring Rebate page for today's amounts before you count on a rebate. United Power customers should check with United Power instead.

Published cost ranges (national)

Angi's 2026 national average for home EV charger installation is $967, with most homeowners paying $555 to $1,380. (Angi, EV charging) Angi's add-on line items, also national:

Item National range
New wiring $500 to $1,500
Electrical panel upgrade, if needed $800 to $2,000
Permits $100 to $200
Mounting pedestal at least $300

Westminster permit fee for a charger circuit

For a job valued at $1,800, the City's 2026 schedule works out as follows (schedule arithmetic, not a quote; counter permits may not carry every line item). (Fee schedule)

Example: job valued at $1,800
Line itemAmount
Building permit fee (valuation table)$53.95
Plan review fee (65% of permit fee)$35.07
Electric permit trade fee (15% of permit fee)$8.09
Electric plan review trade fee (15% of plan review fee)$5.26
Estimated use tax (4.25% of 50% of valuation)$38.25
Total if every line applies$140.62

Questions to ask before you buy a charger

  • What amperage does the charger draw, and does Xcel's rebate cover that model?
  • Does the load calculation show room on the existing panel?
  • Where will the charger go, and how long is the circuit run from the panel?
  • Is the quote including the permit and the load calculation the City asks for?

Frequently asked questions

Do I need a permit for an EV charger in Westminster?

Yes. The City has a Residential Counter, EV Charger permit in eTRAKiT. For a Level 2 charger it asks for a site or floor plan, load calculations for the whole residence and a one-line diagram.

Does Xcel Energy offer a rebate for EV charger wiring in Colorado?

Xcel Energy Colorado offers a Charger and Wiring Rebate that requires enrollment in a qualifying Xcel program. Amounts and terms change, so check Xcel's current rebate page.

How much does EV charger installation cost?

Angi's 2026 national average is $967, with most homeowners paying $555 to $1,380, before any panel upgrade.

Sources

Checked November 18, 2026.

  1. City of Westminster, Building Resources
  2. City of Westminster, EV Charger Permit Submittal Requirements
  3. Xcel Energy Colorado, Charger and Wiring Rebate
  4. Angi, EV Charging Installation Costs (national)
  5. City of Westminster, Building Division Fee Schedule (effective Jan. 1, 2026)